In the morning of Jan. 9, the H1278 and H1287 launched from No.1 Drydock, which was the 1st round of launching in t2015. Meanwhile, H1312 and H1324, the semi-hull of the two vessels successfully completed the stage of the floating in the same dock. Since the last final round of launching, it is after only 35 days when the new round of launching was realized, which achieved the goal of in-dock construction cycle for 10 rounds of launching in 2015.
With the accordance of working plan, H1278 is the last 180 thousand DWT Bulk Carrier for Thenamaris, H1287 is the 12th 180 thousand DWT Bulk Carrier for Frontline. H1312 is the first 180,000 DWT Bulk Carrier for OCEAN BULK and H1324 is the 5th 186,000 DWT Bulk Carrier for U-MING.
This first round of launching in No.1 drydock was completed according to the production schedule, which made a good start for the whole year and laid a solid foundation for shortening the quay construction cycle and achieving the goal of 10 rounds of launching.