description
Current Position:HOME > NEWS > NEWS

The 7th Round of Launching of No.1 Drydock Started

Date:
2014-10-22
From:
chinasws
On Oct.22, SWS carried out the launching of H1277 and H1333, which was the 7th round of launching in No.1 drydock. As followed, H1286 and H1334 were floated successfully. It is reported that, H1277 is the 2nd 180,000 DWT Bulk Carrier built for Thenamaris, the other three 180,000 DWT Bulk Carriers, H1286, H1233 and H1334 are built for Frontline. Confronting the high requirement of quality and tight schedule for H1277, Machinery Installation and Commissioning Dept. Hull-outfitting and Installation Dept, Blasting and Coating Dept. and Erection Dept have overcome many difficulties for guaranteeing the launching and floating of these four vessels. After this successful launching, there is only one step to approach to the whole year's target which is to complete 8 rounds of launching in 2014.