In the morning of June 10, H1266, the third 180,000 t DWT Bulk Carrier built for Frontline came back to the No.3 Outfitting Quay of SWS after her successful sea trial. In the early morning of June 13, H1296, the first 180000 DWT Bulk Carrier built for Thenamaris started her sea trial. These two vessels were launched from No.1 Drydock in SWS on May 4 together, particularly, H1266 took 32 days for outfitting at quayside and spent 5 days in her sea trial as well as H1296 spent 38 days in outfitting at quayside
After launching of H1266 and H1296, all the working departments strictly complied with the plan determined by the company and guaranteed the every working millstone to be completed orderly. The third phase goals on "generator, main engine, anchor windlass, steering gear and boiler" of these two vessels were completed respectively on May 19th and May 11th, which means that the function test of boiler was delivered only 15 days after launching.