SWS accomplished 4 major offshore milestones in the past two weeks.
After 9 days hard work, on May 24th, the drilling rig project H1319 successfully completed leg extension by floating crane at jetty of SWS Offshore. At 9 pm on May 29th, SWS’ first CJ46 drilling rig, project H1368, has completed derrick erection in No. 2 on grand assembly platform. At 2 am on May 31st, drilling rig project H1320 completed cantilever, drillfloor and derrick load test, BOP lifting and installation, CTP lifting and installation. In the evening, CJ46 drilling rig, project H1378, completed cantilever erection.
The successful completion of four milestones not only inspired the morale, but also declared the offshore production targets were successfully delivered in second half of May. In addition, the milestones made full preparation for future launching of H1368.