description
Current Position:HOME > NEWS > NEWS

Two Vessels Launched and One Vessel Floated in SCH

Date:
2013-08-06
From:
chinasws
At 17::30 on July 13, the launching process was officially started with filling water into No.3 Drydock of SCH. Thus, after nearly 3-month hard working, the launching of both H1068 and H1069, which are 9400 container vessels, was successfully completed, and the floating of H1070 which is under-construction in the same drydock was realized. For the successful completion of this launching, all production departments have overcome the great pressure of the fast-paced production and created a good condition for the next dock cycle. In the hot summer, everyone overcome the heat, stick in the workplace to ensure the construction in drydock was conducted smoothly and orderly by helping each other. On the other hand, facing the high standard of requirements and the tight schedule, the construction supervisors won the battle with their professional knowledge and indomitable willpower. After the successful completion of the launching for both H1068 and H1069, all production departments immediately get into the installation work along the quay and continue to work hard for the next milestone.